Notion Timeline Dependencies | Full Setup Guide

Table of content

In this age of highly sophisticated project management tools, Notion, with its multi-faceted platform, stands out due to its unique feature set. One of its most powerful features is timeline dependencies.

With this feature, planning, scheduling and managing projects becomes easier and more efficient. This comprehensive guide will walk you through the process of setting up timeline dependencies in Notion from scratch.

Key Takeaways

  • To activate dependencies, navigate to database settings and click on dependencies.
  • There are three types of dependencies - ”Shift only when dates overlap”, “Shift & maintain time between items”, and “Do not automatically shift”.
  • Additional settings like "Avoid weekends", "Shift using → date property", and "Separate start & end dates" can be utilized for increased project management competency.

Activating Timeline Dependencies in Notion

Getting started with timeline dependencies in Notion is a straightforward process.

  1. Begin by setting up your project database in Notion.
  2. Once this is done, click on the '...' icon on the top right corner of your screen and select 'Database settings' from the dropdown menu.
  3. In the subsequent screen, locate 'Dependencies' in the left pane and click on it. Activate the dependencies by switching on the toggle button on the right.

Different Types of Dependencies

Notion timeline dependencies

Notion provides three different types of timeline dependencies, each offering varying levels of control over your project timelines:

Shift only when dates overlap

This dependency type automatically reschedules tasks if their start and end dates overlap with others. It helps to prevent task collisions and ensure smooth project execution.

Shift & maintain time between items

This type of dependency allows you to set a fixed duration between tasks. If an earlier task is rescheduled, the subsequent tasks will be adjusted accordingly, maintaining the set time gap.

Do not automatically shift

If you prefer to manually manage the timeline of your tasks, this dependency type is for you. It does not cause any automatic shift in tasks, giving you full control over the project timeline.

Other Important Settings

In addition to timeline dependencies, Notion offers a slew of other settings that can help you optimize your project management:

Avoid weekends

If your projects don't operate over the weekend, this setting can help. It ensures that tasks are not scheduled for weekends, helping you maintain a strict Monday to Friday schedule.

Shift using → date property

This feature allows you to adjust your project timeline based on a specific date property. Whether it's a deadline, a start date, or another significant date, this setting lets you shift tasks depending on these important project milestones.

Separate start & end dates

If you have separate start and end dates for your tasks, this setting will allow you to use them separately instead of having a range a single date property.

Conclusion

Timeline dependencies are a powerful feature of Notion that can take your project management skills to the next level. By understanding how to activate dependencies, leverage different dependency types, and use additional settings, you can efficiently plan, schedule, and manage your projects. So start reaping the benefits of timeline dependencies in Notion today!

Frequently asked questions

How can I activate timeline dependencies in Notion?

To activate timeline dependencies in Notion, start by setting up your project database. After that's done, click on the '...' icon on the top right corner of your screen and select 'Database settings' from the dropdown menu. In the screen that pops up next, find 'Dependencies' in the left pane and click on it. To activate the dependencies, switch on the toggle button on the right.

What are the different types of timeline dependencies available in Notion?

Notion provides three types of timeline dependencies. They are 'Shift only when dates overlap' which automatically reschedules tasks if start and end dates overlap with others, 'Shift & maintain time between items' allows you to set a fixed duration between tasks and adjusts subsequent tasks based on reschedules, and 'Do not automatically shift' which gives you full control to manually manage the task timeline.

What additional settings does Notion provide for better project management?

For better project management, Notion provides settings like 'Avoid weekends' that prevent tasks being scheduled on weekends, 'Shift using → date property' that allows you to adjust the project timeline based on specific date properties such as deadlines, and 'Separate start & end dates' feature which lets you set start and end dates from different dates.

Last tutorials

Master Notion, 5 minutes a week

Want to be in the loop with everything Notion? Join the 15,000+ Notioneers on the #1 Notion-focused newsletter.
Every Tuesday, I’ll hit you up with an email, giving you 3 tips on how to make the most of Notion, 2 (awesome) resources, and 1 Tweet of the Week.